Category 2 registrations took effect May 15, 2026. What registered owners now owe, and what to do if a facility was missed.
NERC Category 2 Generator Owner (GO) and Generator Operator (GOP) registrations took effect on May 15, 2026. NERC and the Regional Entities processed registrations in batches from August 2025 through April 2026, and each registered entity received a NERC notification listing it on the Compliance Registry with an effective date of May 15, 2026. Registered Category 2 entities are now subject to the Reliability Standards that apply to them, and the IBR standards bring their own compliance dates over the next several years.
This guide covers who is Category 2, what applies now, and what to do if a facility that meets the criteria was not registered.
Category 2 covers non-BES inverter-based resources that either have or contribute to an aggregate nameplate capacity of 20 MVA or more, connected through a system designed primarily for delivering such capacity to a common point of connection at a voltage of 60 kV or above. BES IBRs were already registered: under inclusion I4 of the BES definition, dispersed power producing resources are BES when they aggregate to more than 75 MVA (gross nameplate) through a system designed primarily for delivering that capacity to a common point of connection at 100 kV or above.
Aggregation is the part most often missed. If several facilities together reach 20 MVA at a common point of connection at 60 kV or above, all of them are Category 2, and each owner and operator registers. For example, two 15 MVA plants sharing a collector system to a common 69 kV point of connection total 30 MVA, so both are Category 2.
NERC disturbance reports, including those on the 2016 Blue Cut Fire and 2017 Canyon 2 Fire events in California and the 2021 and 2022 Odessa events in Texas, found IBRs tripping or reducing output during grid faults. FERC Order No. 901 (October 2023) directed new IBR reliability standards, and in a separate proceeding (Docket No. RR24-2) FERC approved NERC's Rules of Procedure changes to register owners and operators of non-BES IBRs.
NERC publishes Reliability Standards Compliance Dates for Generator Owners & Generator Operators, updated quarterly, which lists finalized and pending compliance dates for Category 2 GO and GOP registrations. Check it for each facility. The IBR-specific standards and their Category 2 dates:
Other standards apply to Category 2 GOs and GOPs on the dates in NERC's compliance dates document, and some are still being revised before they apply. Cybersecurity (CIP) standards are written for BES Cyber Systems; check NERC's current list before assuming any CIP obligation for a non-BES plant. Category 2 entities that meet NERC's Generating Availability Data System (GADS) reporting criteria report GADS data from May 15, 2026.
The registration effective date has passed, but the registration criteria still apply. NERC's FAQ on the Category 2 registration process tells an owner who thinks an asset may meet the criteria, but who was never contacted, to reach out to NERC Registration, which will identify the right Regional Entity. The Regional Entity is set by where the IBR connects to the bulk power system. The Regional Entity collects, through CORES (NERC's Centralized Organization Registration ERO System) or another secure site:
An owner that concludes on its own that a facility does not meet the criteria still submits these documents; the Regional Entity makes the determination. If the GO has not decided who its GOP will be, the Regional Entity will advise it to register as both GO and GOP until that is settled. A project that meets the Category 2 criteria in its first phase and Category 1 (a BES IBR) once later phases reach commercial operation starts with the Category 2 registration.
The maximum civil penalty under section 316A of the Federal Power Act is $1,584,648 per violation per day, the amount FERC set in its January 2025 inflation adjustment. There was no 2026 adjustment: OMB memorandum M-26-11 cancelled the 2026 adjustments because October 2025 CPI data was not available, so agencies continue to use the 2025 amounts.