Computational Load Protection Coordination & Disturbance Monitoring
CLO-003-1 applies to Computational Load Sites, such as data centers, with a total connected Load of 50 MW or more supplied through electrical equipment connected at 100 kV or above. Each Computational Load Owner records breaker position and runs a process that keeps Protection System settings coordinated with the other owners of electrically joined equipment. Whoever owns the main power transformer supplying the site, whether the Computational Load Owner, a Transmission Owner, a Distribution Provider or a Generator Owner, keeps fault and dynamic disturbance recordings. Each entity keeps its recorded data time-synchronized and provides it on request. The standard passed final ballot on October 14, 2026 and was adopted by the NERC Board of Trustees on October 26, 2026; it awaits filing with FERC and FERC approval and is not in force.
Source
NERC Project 2026-02 (final ballot draft, October 2026)October 29, 2026
Requirements
What it means. Each Computational Load Owner has sequence of events recording data at its sites for circuit breaker position (open/close) for the breakers associated with equipment it owns, including buses and, as applicable, the main power transformer(s), on-site generation, and shunt static and dynamic reactive devices.
Evidence an auditor expects. Actual data recordings; documents describing the device interconnections and configurations, which may be a single design standard representative of common installations; or station or equipment drawings.
What it means. Whichever Computational Load Owner, Transmission Owner, Distribution Provider or Generator Owner owns the main power transformer(s) supplying the site has triggered fault recording data on the high side of the main power transformer(s) or the common point(s) of connection, enough to determine phase-to-neutral voltage for each phase, each phase current and the residual or neutral current, and three-phase Real and Reactive Power. The main power transformer is the power transformer and associated equipment that steps the site's voltage down from its nominal transmission or interconnecting system voltage.
Evidence an auditor expects. Actual data recordings or derivations; documents describing the device specifications and configurations, which may be a single design standard; or station or equipment drawings.
What it means. The owner of the main power transformer(s) makes sure its R2 fault records include at least two cycles before the trigger and at least 2.0 seconds in total for the same trigger point, in one record or several; record at least 64 samples per cycle; and trigger on at least neutral (residual) overcurrent, AC phase overvoltage and undervoltage, and overfrequency and underfrequency.
Evidence an auditor expects. Actual data recordings or derivations, or documents describing the device specification and its configuration or settings.
What it means. The owner of the main power transformer(s) has continuous dynamic disturbance recording and storage on the high side of the main power transformer(s) or the common point(s) of connection, enough to determine phase-to-neutral voltage for each phase, each phase current and the residual or neutral current, three-phase Real and Reactive Power flows for all circuits where current is measured, and the frequency of any one of the recorded voltages.
Evidence an auditor expects. Actual data recordings or derivations; documents describing the device specifications and configurations, which may be a single design standard; or station drawings.
What it means. The entity responsible for the R4 data samples inputs at 960 samples per second or more and records electrical quantities at least 60 times per second.
Evidence an auditor expects. Documents describing the device specification, configuration or settings, or actual data recordings for the recording rate.
What it means. The entity responsible for the SER, FR or DDR data synchronizes it to Coordinated Universal Time (UTC), with or without a local time offset, with device clocks within 1 millisecond of UTC.
Evidence an auditor expects. Documents describing the device specification, configuration or setting; time synchronization indication or status; or station drawings.
What it means. The entity responsible for the data provides all requested SER, FR and DDR data to its Transmission Planner, Planning Coordinator, Transmission Operator, Balancing Authority, Reliability Coordinator, Regional Entity or NERC. Data stays retrievable for 20 calendar days, counting the day it was recorded, and is provided within 15 calendar days of a request unless the requestor grants an extension. SER data goes in ASCII CSV format following the standard's Attachment 1; FR and DDR data in CSV with appropriate headers or COMTRADE (IEEE C37.111, 1999 or later); file names follow COMNAME (IEEE C37.232-2011 or later).
Evidence an auditor expects. Actual data recordings; dated transmittals to the requesting entity with formatted records; or documents describing data storage capability, device specification, configuration or settings.
What it means. On discovering a failure of SER, FR or DDR recording capability, the responsible entity restores it within 90 calendar days, or submits a Corrective Action Plan (CAP) to the Regional Entity within 90 calendar days and then carries it out on the CAP timeline.
Evidence an auditor expects. Dated reports of the discovery of a failure, documentation of the date recording was restored, SCADA records, or dated CAP transmittals to the Regional Entity with evidence the CAP was implemented.
What it means. Each Computational Load Owner establishes a process for developing new and revised Protection System settings at its sites so that Protection Systems operate in the intended sequence during Faults. Where settings are applied on a site that electrically joins equipment owned by separate Transmission Owners, Generator Owners or Distribution Providers, the process provides for responding to any owner that proposed settings by identifying coordination issues or affirming that none were found; verifying that identified issues are addressed before implementation; and communicating with the other owners about settings revised because of unforeseen circumstances during implementation or commissioning, Misoperation investigations, maintenance, or emergency replacements after a Protection System component failure.
Evidence an auditor expects. Dated electronic or hard copy documentation showing the process was established.
What it means. Each Computational Load Owner uses its R9 process to develop new and revised Protection System settings for its sites.
Evidence an auditor expects. Dated electronic or hard copy documentation showing the process was used.
A Computational Load Owner always carries R1, R9 and R10. It carries R2 to R4 only if it owns the main power transformer(s) supplying the site. R5 to R8 apply to whoever is responsible for the recorded data, so R6 to R8 cover the owner's R1 SER data in every case. Evidence for R1 to R8 is kept for three calendar years; evidence for R9 and R10 is kept from the last audit onward.
A Generator Owner that owns the main power transformer(s) supplying a Computational Load Site carries R2 to R4 and, for that data, R5 to R8. Its compliance date for R2 to R8 depends on the site's in-service date, as set out in the key dates. Where the site's settings electrically join equipment the Generator Owner owns, the Computational Load Owner's R9 process responds to the Generator Owner's proposed settings and communicates revised settings to it.