Standards Help Center
Frequency and Voltage Protection Settings for Synchronous Generators, Type 1 and Type 2 Wind Resources, and Synchronous Condensers
PRC-024-4 requires Generator Owners and Transmission Owners to set the frequency, voltage and volts per hertz protection applied to synchronous generators, type 1 and type 2 wind resources and synchronous condensers so that it does not trip the Facility inside the no trip zones of Attachments 1 and 2, except for documented and communicated regulatory or equipment limitations and, for voltage protection, settings within a location-specific Transmission Planner study where the Transmission Planner allows less stringent settings. It replaced PRC-024-3 on October 1, 2026, and inverter-based resources are no longer in its scope; their ride-through requirements are in PRC-029-2.
Source
NERC PRC-024-4 (standard page)October 4, 2026
Requirements
What it means. Set applicable frequency protection in accordance with Attachment 1 so that it does not cause the Facility to trip within the no trip zone during a frequency excursion. Attachment 1 gives separate boundaries for the Eastern, Western, Quebec and ERCOT Interconnections, and the area outside the no trip zone is not a must trip zone. Frequency is calculated over a window of time; instantaneous trip settings based on instantaneously calculated frequency are not permissible. The only exception is a regulatory or equipment limitation documented and communicated under R3.
Evidence an auditor expects. Dated setting sheets, calibration sheets, calculations or other documentation showing the frequency protection is set per R1.
What it means. Set applicable voltage protection in accordance with Attachment 2 so that it does not cause the Facility to trip within the no trip zone during a voltage excursion at the high side of the GSU or main power transformer. If the Transmission Planner allows less stringent settings, the protection may be set within the voltage recovery characteristics of a location-specific Transmission Planner study, and a documented and communicated limitation under R3 is also an exception. In the Quebec Interconnection, Regional Variance D.A.2 replaces R2 and uses Attachment 2A.
Evidence an auditor expects. Dated setting sheets, voltage-time boundaries, calibration sheets, coordination plots, dynamic simulation studies, calculations or other documentation.
What it means. Document each known regulatory or equipment limitation that prevents the Facility from meeting R1 or R2, with support such as study results, experience from an actual event or manufacturer's advice. Limitations caused by the setting capability of the protective relays themselves do not count; limitations originating in the protected equipment do. Communicate the limitation, or its removal, to the Planning Coordinator and Transmission Planner within 30 calendar days of identifying it, of a repair or replacement that removes it, or of a limitation created or adjusted by consumption of the cumulative turbine life-time frequency excursion allowance.
Evidence an auditor expects. A dated email or letter to the Planning Coordinator and Transmission Planner containing the documentation, such as study results, event experience or manufacturer's advice.
What it means. Provide the protection settings associated with R1 and R2 to the Planning Coordinator or Transmission Planner that models the Facility within 60 calendar days of a written request, and within 60 calendar days of any change to those previously requested settings, unless the requester says changes need not be reported.
Evidence an auditor expects. Dated emails, correspondence or other evidence of the transmittal, and copies of the requests received.
PRC-024-4 does not apply to inverter-based resources: its implementation plan says the revision removed IBRs from its applicable facility types, and IBR ride-through is now addressed in PRC-029-2.
Related guidance
A question about how this standard applies to a specific plant, model or deadline? Bring it to a GridStrong engineer.