Standards Help Center

PRC-029-2

Frequency and Voltage Ride-through Requirements for Inverter-Based Resources

PRC-029-2 requires each applicable inverter-based resource to Ride-through, that is stay connected and keep operating, through the voltage and frequency excursions defined in its attachments, subject to the exceptions listed in R1 and any accepted R4 hardware limitation. It also sets how the resource delivers real and reactive power during those excursions. The Generator Owner shows both in the plant's design and in its operation. PRC-029-2 replaced PRC-029-1 on October 1, 2026.

Who it applies to

  • Generator Owners of Bulk Electric System (BES) inverter-based resources.
  • Generator Owners of non-BES inverter-based resources that have, or contribute to, an aggregate nameplate capacity of 20 MVA or more, connected through a system designed primarily to deliver that capacity to a common point at 60 kV or above (these are generally the facilities whose owners register as Category 2 Generator Owners; applicability follows the facility test above).

Key dates

  • October 1, 2026: PRC-029-2 effective date. PRC-029-2 replaced PRC-029-1, which never took effect: FERC approved PRC-029-2 and the retirement of PRC-029-1 on September 30, 2026 (Docket No. RD26-10-000), one day before PRC-029-1's own October 1, 2026 effective date. The implementation plan still counts its deadlines from the PRC-029-1 effective date, so wherever a row below says so, the date is October 1, 2026.
  • October 1, 2026: Generator Owners of BES inverter-based resources comply with the design portion of R1 to R3. The implementation plan carries these R1 to R3 dates forward unchanged from PRC-029-1, keyed to the PRC-029-1 effective date, which is October 1, 2026 in the United States.
  • January 1, 2027: Generator Owners of applicable non-BES inverter-based resources comply with the design portion of R1 to R3, by the later of this date or the PRC-029-1 effective date (October 1, 2026), so January 1, 2027.
  • Operational portion of R1 to R3: applies once the entity has established the required disturbance monitoring equipment capabilities for the resource under the PRC-028-1 implementation plan.
  • October 1, 2027: a Generator Owner with an applicable inverter-based resource in service by October 1, 2026, and responsible for compliance with Reliability Standards for that resource on or before that date, submits supporting documentation for any applicable hardware limitation no later than 12 months after the PRC-029-1 effective date (October 1, 2026), so by October 1, 2027. This applies to BES and non-BES resources alike.
  • 90-day track: a resource in service by October 1, 2026 whose Generator Owner was not yet responsible for compliance on that date, and a resource that enters service after October 1, 2026 and qualifies under R4 (the long-lead path), submit supporting documentation for any hardware limitation by the later of 90 calendar days after the date the Generator Owner is required to comply with Reliability Standards for the resource, or the PRC-029-2 effective date (October 1, 2026).

GridStrong procedure

GS-PRC-029-0001

A template procedure written to the standard. Send it back to us with your document template and we convert it into your organization's format and design automatically, with the roles mapped to your team.

Thanks. The procedure is on its way to your inbox. If it has not arrived in a few minutes, check your spam folder or email help@gridstrong.ai.
Something went wrong. Email help@gridstrong.ai and we will send the procedure.

Source

NERC PRC-029-2 (standard text, PDF)

October 29, 2026

Requirements

What each requirement asks for, in plain English.

R1 · Ride through voltage excursions

What it means. Each inverter-based resource must Ride-through, meaning stay connected and keep operating, anywhere inside the must ride-through zone of Attachment 1, including no trip on phase-locked-loop loss of synchronism. The standard lists the exceptions: disconnecting to clear a fault, a hardware limitation accepted under R4, a positive-sequence phase-angle jump of more than 25 electrical degrees from a non-fault switching event, and Volts per Hz at the high side of the main power transformer above 1.1 per unit for longer than 45 seconds or above 1.18 per unit for longer than 2 seconds.

Evidence an auditor expects. For design: dated inverter and plant protection setting sheets compared with the Attachment 1 voltage-time boundaries, engineering, procurement and construction (EPC) design documentation and dynamic simulation studies. For operation: sequence of events, fault and dynamic disturbance records for each voltage excursion, and, where the phase-jump exception is used, written confirmation from the Transmission Planner (TP), Reliability Coordinator (RC), Planning Coordinator (PC) or Transmission Operator (TOP) that a non-fault switching event occurred.

R2 · Deliver the right current during a voltage excursion

What it means. While voltage at the high side of the main power transformer stays in the continuous operation region, each inverter-based resource keeps delivering the lesser of its pre-disturbance or available real power (except during a frequency excursion), keeps delivering reactive power up to its limit and per its controller settings, and, below 0.95 per unit, follows its configured real or reactive power priority when it cannot deliver both. In the mandatory operation region it exchanges current up to its maximum capability on the affected phases, for both balanced and unbalanced disturbances, with reactive power priority by default unless its TP, PC, RC or TOP requires real power priority. In the permissive operation region it may enter current blocking only if needed to avoid tripping, and must restart current exchange within five cycles after positive-sequence voltage returns to the continuous or mandatory operation region. It must not itself push voltage above the high-voltage limits on recovery, and, once voltage returns to the continuous operation region, it restores real power to the lesser of its pre-disturbance or available level within 1.0 second, unless its TP, PC, RC or TOP sets a different level or time.

Evidence an auditor expects. Controller settings for real and reactive power priority, current injection and current blocking, original equipment manufacturer (OEM) capability documentation, and simulation results or event records showing the response.

R3 · Ride through frequency excursions

What it means. Each inverter-based resource must Ride-through, staying connected and operating, while frequency at the high side of the main power transformer stays inside the Attachment 2 must ride-through zone and the absolute rate of change of frequency is 5 Hz per second or less, unless an R4 hardware limitation applies. RoCoF (rate of change of frequency) is the average rate of change of calculated system frequency over 0.1 second or longer, and is not calculated during fault occurrence and clearance.

Evidence an auditor expects. Dated frequency and RoCoF protection setting sheets compared with Attachment 2 and the calculations behind them, plus disturbance monitoring records showing the plant's actual response to each frequency excursion.

R4 · Document hardware limitations

What it means. R4 applies to a Generator Owner whose inverter-based resource has known hardware limitations that prevent it from meeting Ride-through criteria in R1 to R3 and requires an exemption from specific Ride-through criteria, and that either is in service by the effective date of PRC-029-1 (October 1, 2026 in the United States), or is in service after that date and has both an interconnection agreement executed by that date and an equipment procurement contract for the hardware causing the limitation executed before September 1, 2025 (the United States date). The Generator Owner documents: identifying information of the resource (facility name and the Generator Owner's NERC Compliance Registry (NCR) number); which aspects of the Ride-through requirements the resource would be unable to meet and the capability of the hardware due to the limitation; and technical documentation verifying the limitation is due to hardware that would need to be physically replaced to meet all Ride-through criteria, and that it cannot be remedied by software updates or setting changes. It provides a copy to its Planning Coordinators, Transmission Planners, Transmission Operators, Reliability Coordinators and the Compliance Enforcement Authority (CEA); material the equipment manufacturer considers proprietary goes only to the CEA. The submission deadlines are set in the implementation plan (see the key dates above). It answers requests for more information within 90 days, gives the PC, TP, TOP and RC a copy of the CEA's acceptance within 90 days of receiving it, and, if it later replaces the hardware causing an accepted limitation, documents and communicates the change to the PC, TP, TOP and RC within 90 days. The exemption for that criterion then no longer applies. The hardware causing the limitation is understood as an integrated system of components: a combination in which replacing any subset of components would not remove the documented limitation.

Evidence an auditor expects. Technical evidence such as equipment vendor documentation of the hardware limitation, written engineering analysis, test results, or operational data supported by an engineering analysis; evidence of the submission to the CEA; for a resource in service after October 1, 2026, the fully executed interconnection agreement and procurement contract that establish eligibility; and dated transmittals to each recipient with their requests and responses.