MOD-026-2 Dynamic Model Verification and Validation

Dynamic models and the documentation of model verification and validation, prepared against the Transmission Planner's dynamic model requirements and provided to the Transmission Planner.

About this module

What this module covers.

MOD-026-2 took effect April 1, 2026 and replaced MOD-026-1 and MOD-027-1. This module provides MOD-026-2 model verification and validation support: dynamic models and accompanying documentation for generating facilities, including inverter-based resources, prepared against the Transmission Planner's dynamic model requirements.

At a glance

Module: 068
Kind: Modeling studies
Governing body: NERC
Applies to: Operating plants
Typical time: Two to three weeks, all in, including your review

Dashboard capabilities

  • Automated Compliance Workflow for MOD-026-2
  • Model Workspace Management: your plant's simulation model files kept in one dashboard workspace, with version tracking

Support services

What GridStrong does inside this module.

  • Advise on data requirements.
  • Develop and verify plant-level model.
  • Run simulation studies.
  • Tune model parameters.

Final deliverables

  • Model validation report.
  • Tuned plant-level models.
  • Compiled measurement results.

What we need from you

  • Single-line diagram.
  • Unit type(s) and ratings.
  • Technical manuals.
  • Control and protection settings.
  • Measured test or disturbance recordings used to verify the models.

Assumptions and considerations

How the scope is bounded.

  • You supply the measured test or disturbance data used to verify the models; positive-sequence and electromagnetic transient (EMT) models are also cross-checked against each other.
  • Runs in both PSCAD and PSS/E.

Run this module on one site.

Tell us the plant and the deadline. An engineer confirms the inputs, the schedule and what the Dashboard needs from you.