PJM Interconnection Module Package

PSS/E and PSCAD model packages and study support through PJM's Cycle process under Manual 14H, from the Application Phase and Decision Points I to III to the Generation Interconnection Agreement and commercial operation.

About this module

What this module covers.

This package covers modeling and support for one or more interconnection requests in the PJM Interconnection (PJM) region. PJM studies new generation and storage requests in a cluster-based Cycle process under Tariff Part VIII and Manual 14H, where each Cycle consists of the Application Phase, Phase I, Decision Point I, Phase II, Decision Point II, Phase III, Decision Point III and the Final Agreement Negotiation Phase. PJM requires a PSS/E dynamic model package with the application and, from Cycle 01 onward, a PSCAD model at Decision Point II, each built and tested to PJM's own guidelines. Navigating this process correctly requires engineering expertise in how to design, model and plan a project across each stage. This package covers five stages, from the application through the Generation Interconnection Agreement (GIA), commercial operation and post-commercial operation model updates.

At a glance

Module: 089
Kind: Interconnection studies
Governing body: PJM
Applies to: Before and after commercial operation
Typical time: Follows the PJM interconnection calendar

Dashboard capabilities

  • Automated Compliance Workflow for PJM MQT
  • Model Workspace Management: your plant's simulation model files kept in one dashboard workspace, with version tracking
  • PSCAD Simulations
  • PSS/E Simulations

Support services

What GridStrong does inside this module.

Stage 1: Application Phase, Phase I System Impact Study and Decision Point I

  • Support you through the Application Phase of the Cycle under Tariff Part VIII and Manual 14H, including review of the technical information you enter in PJM's data submission tool (Point of Interconnection, Maximum Facility Output (MFO), Capacity Interconnection Rights, fuel type, storage charging, MWh and hour class, equipment configuration) and responses to PJM's deficiency review. You submit the application.
  • Develop the plant power flow (.idv) and dynamic (.dyr) models per the PJM Dynamic Model Development Guidelines, avoiding models on PJM's Unacceptable Models List. For a non-synchronous facility in a Cycle under PJM's Order No. 2023 compliance revisions, prepare the appropriately parameterized PSS/E library model and integrate the validated user-defined root-mean-square (RMS) model from the original equipment manufacturer (OEM), since the application must carry both, plus a validated electromagnetic transient (EMT) model where PJM requires one with the application.
  • Perform the PJM Model Testing Requirements on a single machine infinite bus: MFO assessment, power factor assessment, flat start test, voltage ride-through test, momentary cessation review and primary frequency response check.
  • Prepare the Dynamic Model Report, the Dynamic Model Checklist and the comparison table of Data Application form values against PSS/E model values that PJM requires to avoid data deficiency notices.
  • Coordinate with inverter, turbine and plant controller manufacturers to obtain models, parameters and reactive capability curves that match the equipment in the application.
  • Prepare the load flow and short-circuit data PJM requests through its data submission tool.
  • Support you at the scoping meeting PJM holds to confirm the Point of Interconnection for modeling purposes.
  • Review the Phase I System Impact Study load flow results and the Phase I base case (once our engineers have PJM Critical Energy/Electric Infrastructure Information (CEII) access) and advise you on your Decision Point I choices.
  • At Decision Point I, update the dynamic, short-circuit and load flow data for any modification Manual 14H allows and prepare the data PJM needs for the Phase II System Impact Study.
  • Prepare the model package PJM requires when you pursue one of its parallel processes: Surplus Interconnection Service, Replacement Generation Interconnection Service or the temporary Expedited Interconnection Track, whose application also requires a PSCAD model built to the PJM EMT Model Development Guidelines.

Stage 2: Phase II and Phase III System Impact Studies and Decision Points II and III

  • Review the Phase II System Impact Study results, including the stability and short circuit analyses, and support you in resolving identified plant instability through model and control-setting changes within the modifications Manual 14H allows.
  • Develop the PSCAD model of the plant up to the Point of Interconnection per the PJM EMT Model Development Guidelines for submission at Decision Point II.
  • Perform PJM's PSCAD Model Quality Tests (functional tests, fault ride-through, voltage ride-through profiles, system strength, phase angle change, rate of change of frequency and frequency ride-through settings) and benchmark the PSCAD model against the PSS/E model.
  • Prepare the combined Model Quality Tests and Benchmark Report and coordinate with the model supplier on the PSCAD Model Requirements Checklist, which PJM requires the supplier to complete as an attestation.
  • Update the PSS/E and PSCAD models for any Permissible Technological Advancement you elect at Decision Point II.
  • Provide model data to support an Affected System study when PJM notifies you that one is required.
  • Review the Phase III System Impact Study retool of load flow, short circuit and stability results, and any EMT study PJM performs on the plant, and respond to PJM data requests before Decision Point III, when no modifications are permitted.

Stage 3: Final Agreement Negotiation Phase and GIA Implementation

  • Review the technical specifications in the draft GIA tendered by PJM against the studied model.
  • Track equipment and setting changes during detailed design and procurement and update the PSS/E and PSCAD models to match.
  • Coordinate with manufacturers and the engineering, procurement and construction (EPC) contractor so plant controller, inverter and protection settings stay consistent with the models PJM studied.
  • Prepare the model package for a Necessary Study when you plan a modification under the GIA, so PJM can determine whether it has a permanent material impact on the Transmission System.

Stage 4: Initial Operation, Commercial Operation and As-Built Data

  • Update the PSS/E (library and user-defined) and PSCAD models to as-built design parameters and the settings after commissioning, and include in the as-built package the Factory Acceptance Test report you provide for each main power transformer.
  • Prepare the as-built electrical modeling data that the GIA requires within one month following commercial operation.
  • Perform the as-built PSCAD Model Quality Tests and PSCAD-PSS/E benchmark and prepare the Parameter Verification Report where PJM's EMT guidelines require them.
  • Compare commissioning settings with the studied model and flag any difference that PJM may treat as a qualified change to review before commercial operation.
  • Prepare the reactive capability curves PJM requires before commercial operation and, where the facility meets the testing criteria in Manual 14D Attachment E, support the reactive capability test due within 90 days after commercial operation.

Stage 5: Post-Commercial Operation Model Tuning and Necessary Studies

  • Tune the models against field test results in accordance with North American Electric Reliability Corporation (NERC) MOD-026-2, for submission no later than one year after commercial operation; MOD-026-2 took effect April 1, 2026 and replaced MOD-026-1 and MOD-027-1.
  • Update models after any change to inverter-based resource control settings or equipment, the addition of energy storage to a wind or solar facility, or an operation mode conversion, and prepare the full revised deliverables with a change report for the Necessary Study or Surplus request.
  • Support the periodic reactive capability tests Manual 14D requires.

Final deliverables

  • Stage 1: PSS/E .idv and .dyr files with case setup files (.raw, .sav, .cnv, .snp, .sld) and the user-defined model files (both RMS models for a non-synchronous facility in a Cycle under PJM's Order No. 2023 compliance revisions), compatible with the PSS/E version PJM lists for your Cycle; Dynamic Model Report with Dynamic Model Checklist and PJM Model Testing Requirements results; load flow and short-circuit data for PJM's data submission tool; deficiency responses; Phase I results review memo; updated model package at Decision Point I when you modify the request.
  • Stage 2: Phase II results review and mitigation memo; PSCAD model, Model Quality Tests and Benchmark Report and all PSCAD case files for Decision Point II (the model supplier completes the PSCAD Model Requirements Checklist); updated model package for any Permissible Technological Advancement; Phase III results review memo.
  • Stage 3: Updated PSS/E and PSCAD models reflecting design and procurement changes; Necessary Study model package when needed; technical review notes on the draft GIA.
  • Stage 4: As-built PSS/E library and user-defined models and as-built PSCAD model; as-built Model Quality Tests and Benchmark Report and Parameter Verification Report where required; reactive capability curves and reactive test support report.
  • Stage 5: Tuned model set and validation report per MOD-026-2; revised model deliverables with a change report for each qualified change.

What we need from you

  • Project information such as the Project Identifier once PJM assigns it, Point of Interconnection (substation or line tap and voltage), Transmission Owner zone, requested Maximum Facility Output and Capacity Interconnection Rights, fuel type(s) and proposed in-service date.
  • For storage: whether and how it charges from the Transmission System, primary frequency response operating range, MWh stockpile and hour class.
  • Inverter or turbine make and model, datasheets and reactive capability (P-Q) curve at the ambient temperature PJM specifies.
  • OEM PSS/E and PSCAD models with user guides, block diagrams and parameter descriptions; plant controller models and settings.
  • Single-line diagram; inverter step-up and main power transformer data (impedance, winding configuration, tap changer settings) and Factory Acceptance Test reports; collector system impedances; attachment line impedance and length; reactive compensation devices; station service and auxiliary loads.
  • Control narratives, voltage and frequency protection settings, momentary cessation settings and any documented equipment limitation.
  • Transmission Owner technical requirements for the interconnection.
  • A PJM CEII Authorization Form from you naming our engineers, so each can request the Cycle base case through PJM's CEII process.
  • PJM study results, deficiency notices and data requests; commissioning test records and as-left settings.

Assumptions and considerations

How the scope is bounded.

  • We provide the models compatible with the PSS/E version PJM's Dynamic Model Development Guidelines list for your Cycle (PSS/E 35.3.2 for Cycle 01) and in a format compatible with PSCAD/EMTDC per the PJM EMT Model Development Guidelines.
  • The work follows the Cycle process under Tariff Part VIII and Manual 14H Rev 07. The Cycle 01 application deadline (April 27, 2026) has passed and Cycle 01 Phase I started September 28, 2026, so a request filed now enters a later Cycle whose Application Deadline PJM posts at the start of the prior Cycle's Phase II, at least 180 days in advance. The Federal Energy Regulatory Commission (FERC) accepted PJM's Order No. 2023 compliance revisions to Tariff Part VIII to take effect at the start of the next Cycle, so that Cycle runs under the revised Part VIII and the Manual 14H revision that implements it; we follow those documents as PJM publishes them.
  • Manuals 14A and 14E are retired and their contents are in Manual 14H; Manual 14G applies only to older requests, PJM plans to retire it on November 30, 2026, and it is outside this module.
  • Inverter-based resource requests submitted on or after June 22, 2027 must meet the IEEE 2800-2022 based requirements in Manual 14H Attachment L; we reflect those requirements in the models where they apply.
  • We prepare data, models and reports; you submit them through PJM's data submission tools and provide all deposits, security, Site Control, permits and other readiness evidence.
  • We support only the modifications Manual 14H allows at each Decision Point; any other change requires you to withdraw and resubmit in a later Cycle.
  • We rely on timely and accurate information from you, including information from your OEMs and EPC contractors; we assume no responsibility or liability for the accuracy of information supplied by you or your suppliers.
  • We do not guarantee the accuracy or quality of any models supplied by the OEMs.
  • This scope includes one round of corrections with the OEMs and EPC contractors per model; further rounds are additional support, approved in writing.
  • PJM revises its manuals and model guidelines frequently; we follow the revision in effect when each package is prepared, and a new PJM requirement may change the scope.
  • We use engineering judgment and best practices.