CAISO Interconnection Module Package

GE PSLF and PSCAD models, model quality tests and study support through CAISO's cluster process under the Resource Interconnection Standards, through commercial operation.

About this module

What this module covers.

This package covers modeling and support for one or more interconnection requests to the California Independent System Operator (CAISO) Controlled Grid. For Queue Cluster 15 and later clusters, CAISO processes requests under the Resource Interconnection Standards (RIS) in Tariff Appendix KK, the appendix CAISO created for its Order No. 2023 compliance and has since amended through its Interconnection Process Enhancements filings. A request enters in the annual Cluster Application Window, where CAISO checks it for completeness; during the Customer Engagement Window that follows, CAISO scores it against the Cluster Study criteria (with an auction to break ties), technically validates the requests that pass and holds Study Area Scoping Meetings; the request then moves through the Cluster Study, the annual reassessment and any Cluster Restudy, the Interconnection Facilities Study and Transmission Plan (TP) Deliverability allocation, and the Generator Interconnection Agreement (GIA). Navigating this process correctly requires engineering expertise in the GE PSLF and PSCAD models CAISO requires and the model quality tests (MQT) CAISO applies to new requests, modification requests and operating resources. This package covers the five stages below, from the Interconnection Request through Trial Operation, Commercial Operation and post-commercial operation model updates.

At a glance

Module: 090
Kind: Interconnection studies
Governing body: CAISO
Applies to: Before and after commercial operation
Typical time: Follows the CAISO interconnection calendar

Dashboard capabilities

  • Automated Compliance Workflow for CAISO MQT
  • Model Workspace Management: your plant's simulation model files kept in one dashboard workspace, with version tracking
  • PSCAD Simulations

Support services

What GridStrong does inside this module.

Stage 1: Cluster Application Window and Customer Engagement Window

  • Support you through the annual Cluster Application Window (October 1 to October 15), including CAISO's completeness check, and the ninety-day Customer Engagement Window that follows, including the Cluster Study Criteria Evaluation and any auction, Technical Validation and the Study Area Scoping Meeting.
  • Screen candidate Points of Interconnection against CAISO's posted injection capacity heatmap and the Transmission Zone single-line diagrams and Area Deliverability Constraint data CAISO publishes by September 1, and support your choice of the definitive Point of Interconnection (POI), due ten days after the window closes.
  • Coordinate with inverter, turbine and power plant controller manufacturers to obtain the models, settings and data the request requires.
  • Develop the plant load flow model in GE PSLF .epc format, with an explicit interconnection line and substation transformers, an equivalent collector system, pad-mount transformer and generator, and all plant-level reactive devices, following CAISO's IBR (inverter-based resource) Dynamic Model Review Guideline.
  • Develop the dynamic model in GE PSLF .dyd format using generic library models approved by the Western Electricity Coordinating Council (WECC) (converter, electrical control, plant controller, voltage and frequency protection, and wind turbine models where applicable), and integrate the PSLF user-defined model supplied by the original equipment manufacturer (OEM) and the validation evidence (attestations or test data) that Appendix KK requires for non-synchronous facilities. For synchronous units, model the generator, exciter, governor and power system stabilizer per Attachment A.
  • Perform CAISO's model quality tests with the CAISO IBR Dynamic Model Validation Procedure: flat run, bump test, plant controller voltage or reactive power reference step, frequency reference step and voltage ride-through playback test, and produce the plots the Interconnection Request requires.
  • Review voltage and frequency ride-through protection settings against the PRC-029 ride-through envelopes with CAISO's spreadsheet tool.
  • Develop the reactive power capability document and the load flow plot of requested MW at the Point of Interconnection, and evaluate reactive capability against the Large Generator Interconnection Agreement (LGIA) Article 9.6.1 power factor design criteria: 0.95 leading to 0.95 lagging at the high side of the generator substation for asynchronous facilities, and 0.95 leading to 0.90 lagging at the generator terminals for synchronous units.
  • Prepare generator short-circuit data, transformer data and the remaining Attachment A technical data in the Excel format CAISO requires, and check the site drawing and single-line diagram for consistency with the models.
  • Prepare the requested storage operating assumptions (charging or not at peak load) and the description of the control technologies that enforce them, where the plant includes storage.
  • Prepare responses to CAISO and Participating Transmission Owner (Participating TO) validation notices on modeling errors, inaccurate data or unusable files within the cure period, and support you at the Study Area Scoping Meeting. You submit the request, all attachments and all responses through GRIP.

Stage 2: Cluster Study, Annual Reassessment/Cluster Restudy and Interconnection Facilities Study

  • Review the Cluster Study power flow, short circuit and stability databases and workpapers that CAISO provides to you on request, and review the Cluster Study Report results (short circuit, stability, power flow including off-peak, and On-Peak Deliverability Assessment).
  • Identify plant-side mitigation options for study findings, such as reactive devices, control settings or Interconnection Service Capacity below Generating Facility Capacity, and support you at the Cluster Study Report Meeting and any Cluster Restudy Report Meeting.
  • Prepare the updated Attachment A models and technical package for modification requests and Permissible Technological Advancements, including CAISO model quality test results.
  • Update models and technical data for the Appendix B Data Form after the Reassessment/Restudy Report and for the Interconnection Facilities Study Agreement.
  • Review the draft Interconnection Facilities Study Report and prepare technical comments within the thirty-day comment period.

Stage 3: Generator Interconnection Agreement and Construction

  • Review the technical requirements in the GIA (Appendix LL or MM), including the ride-through, power factor and data recording requirements for asynchronous facilities in LGIA Appendix H or Small Generator Interconnection Agreement (SGIA) Attachment 7, against the plant design and models.
  • Update the GE PSLF models to the final equipment, firmware and settings, rerun the CAISO model quality tests, and prepare the updated information submission due no later than 180 calendar days before Trial Operation.
  • Prepare the Generator Dynamic Model File and PSLF load flow data for the CAISO New Resource Implementation (Full Network Model) submission, and the inverter control and protection settings documentation.
  • Develop the plant PSCAD electromagnetic transient (EMT) model per the CAISO EMT Modeling Requirements, including the site-specific test case and the fault, voltage or reactive power reference step and frequency or active power reference step tests, and benchmark the PSCAD results against the GE PSLF model.
  • Provide model and data support for a Limited Operation Study when you seek to operate before your Network Upgrades are complete, and for modification requests during construction.

Stage 4: Trial Operation and Commercial Operation

  • Update the models with as-built and as-tested data and prepare the information supplementation required before Trial Operation.
  • Prepare test plans for and analyze the tests CAISO requires: for Category 1 and 2 units under the Business Practice Manual (BPM) for Transmission Planning Process, real and reactive power capability verification (staged test or operational data) and the plant volt/var and active power/frequency control tests under the WECC Generating Facility Data, Testing and Model Validation Requirements, with test reports due within twelve months after the Commercial Operation Date (COD); and, for synchronous units, the open circuit step voltage test before Trial Operation.
  • Validate and tune the GE PSLF and PSCAD models against the test results.
  • Provide as-built impedances, control settings and transformer tap settings in the models for the as-built package due within 120 calendar days after the Commercial Operation Date.

Stage 5: Post-Commercial Operation

  • Prepare the generator modeling data package under the BPM for Transmission Planning Process (data template, .epc and .dyd initialization snapshot, and the no-fault run output spread table), due within 120 calendar days after the Commercial Operation Date or CAISO's data request, whichever is later, and the test reports and PSCAD EMT model due within twelve months of the same trigger.
  • Prepare responses to CAISO and Participating TO deficiency notices on submitted model data.
  • Update models after any change to IBR control settings, protection settings or equipment, validate them with the CAISO IBR Dynamic Model Validation Procedure, and prepare the post-COD modification technical package (revised Attachment A, GE PSLF models and validation results).
  • Support the periodic tests and model updates: real and reactive capability every five years and dynamic stability every ten years.

Final deliverables

  • Stage 1: Plant models in GE PSLF format (.epc load flow and .dyd dynamic, integrating the OEM-supplied user-defined model); a CAISO model quality test report with the flat run, bump, reference step, frequency step, voltage ride-through and MW at POI plots; a reactive power capability document; the Attachment A technical data workbook; a Point of Interconnection screening memo; draft responses to validation notices.
  • Stage 2: A study results review memo with plant-side mitigation options; updated models and technical packages for modification requests; Appendix B Data Form technical inputs; technical comments on the draft Interconnection Facilities Study Report.
  • Stage 3: Updated GE PSLF models and model quality test report for the pre-Trial Operation submission; New Resource Implementation model files; inverter control and protection settings documentation; a PSCAD EMT model with documentation, test case and PSLF-to-PSCAD benchmark report; Limited Operation Study model support where requested.
  • Stage 4: As-built and as-tested model updates; test plans; a model validation report from test results.
  • Stage 5: The Transmission Planning Process generator modeling data package (data template, initialization snapshot, no-fault run table, test reports, PSCAD EMT model); post-COD modification technical packages; periodic test and model update reports.

What we need from you

  • Project information: project name, location and GPS coordinates, Point of Interconnection and voltage, requested Deliverability Status, Interconnection Service Capacity, and proposed In-Service, Trial Operation and Commercial Operation Dates.
  • Site drawing and single-line diagram, including collector feeders, step-up transformers, capacitor banks and protection devices.
  • Inverter, turbine and synchronous generator data sheets, P-Q (real and reactive power) capability curves and short-circuit data (maximum fault current for inverters).
  • Main and pad-mount transformer data and test reports, collector system equivalent impedance data, and gen-tie line data (including engineering details of any shared gen-tie upgrade).
  • OEM GE PSLF generic library models and PSLF user-defined models with OEM validation attestations; OEM PSCAD models with library files, documentation and real-code status; model manuals.
  • Power plant controller settings and control narratives; voltage and frequency protection settings; relay settings.
  • Storage charging operating assumptions and the control technologies that enforce them, where applicable.
  • Commissioning and staged test data, as-built drawings and final equipment settings.

Assumptions and considerations

How the scope is bounded.

  • This module follows CAISO Tariff Appendix KK (Resource Interconnection Standards) as of August 5, 2026, which governs Queue Cluster 15 and later clusters. Requests in Queue Cluster 14 or earlier follow Appendix DD and the GIDAP (Generator Interconnection and Deliverability Allocation Procedures) BPM and are outside this module.
  • The Resource Interconnection Standards BPM is still a draft (Proposed Revision Request 1695, on hold). Until CAISO adopts it, we follow Appendix KK, CAISO notices and the GRIP External User Guide, and we adjust when the BPM is final.
  • CAISO accepts Queue Cluster requests only in the annual October 1 to October 15 Cluster Application Window. The 2026 window has closed, so a request prepared now targets the next annual window.
  • For Queue Cluster 16, CAISO accepts a temporary placeholder in GRIP in place of the PSLF user-defined model and will announce by market notice when the user-defined model is due and must be validated by CAISO and the Participating TO. For a Queue Cluster 16 request, we prepare the user-defined model package and its validation evidence by that date; for later clusters, we prepare it with the Interconnection Request, as Appendix KK requires.
  • We provide the models in GE PSLF format (.epc load flow and .dyd dynamic), the only steady-state and dynamic formats CAISO accepts; CAISO does not accept PSS/E files in place of PSLF. Model quality tests run with CAISO's EPCL test package, which supports PSLF Classic and Advanced UI.
  • PSCAD models will be compatible with PSCAD version 4.6.3 or higher, compiled with Intel Fortran version 12 or higher, and capable of running at time steps from 10 to 20 microseconds, per the CAISO EMT Modeling Requirements.
  • We apply the versions of the CAISO IBR Dynamic Model Validation Procedure and IBR Dynamic Model Review Guideline posted at the time of each submission; WECC has retired the repc_b model, and the August 2026 revision of the Guideline bars it from future submissions. The Participating TO performs the WECC full-loop test; we prepare responses to its findings.
  • We prepare models, data and technical packages; you submit them through GRIP, the Resource Interconnection Management System (RIMS) and the CAISO and Participating TO channels, and sign all affidavits, attestations and agreements. Deposits, financial security, site control and commercial scoring documentation are your responsibility.
  • Our access to Interconnection Base Case Data, study databases and Study Area Scoping Meetings requires a CAISO Transmission Planning non-disclosure agreement that names us as your consultant, plus a WECC confidentiality agreement where CAISO requires one; you confirm the engagement to CAISO.
  • Fast Track Process and distribution-connected (Wholesale Distribution Access Tariff) requests are outside this module. You contract Affected System studies with the Affected System Operator; we provide model and data support.
  • We rely on timely and accurate information from you, including OEM models and data; we assume no responsibility or liability for the accuracy of information supplied by you or your suppliers.
  • We do not guarantee the accuracy or quality of any models supplied by the OEMs.
  • This scope includes one round of corrections with the OEMs and engineering, procurement and construction (EPC) contractors per model deliverable; further rounds are additional support, approved in writing.
  • We use engineering judgment and best practices where CAISO documents leave a choice open.