Southern Company Interconnection Module Package

PSS/E and PSCAD model packages, model performance attestation and study support through the Southern Companies' Annual Cluster Study, from the Cluster Request Window to Commercial Operation.

About this module

What this module covers.

This package covers modeling and support for one or more interconnection requests to the Southern Companies' Transmission System (Alabama Power Company, Georgia Power Company and Mississippi Power Company) under the Southern Companies Open Access Transmission Tariff. A Large Generating Facility (more than 20 MW) enters through the Annual Cluster Study under the Standard Large Generator Interconnection Procedures (LGIP): the Cluster Request Window, the Customer Engagement Window and its Scoping Meeting, the Cluster Study, any Cluster Restudy, and the Interconnection Facilities Study, followed by the Generator Interconnection Agreement (GIA). You and Southern Company Transmission (SCT) then implement the GIA through the Commencement of Work, Interconnection In-Service, Initial Synchronization and Trial Operation phases to SCT's approval of readiness for Commercial Operation. For inverter-based resources (IBRs), SCT requires site-specific PSS/E standard library, PSS/E user-defined and PSCAD models with a model performance attestation report at the interconnection request, followed by as-planned, as-built and as-left models during implementation; we call that attestation Southern Company's Model Quality Assessment (MQA). This package covers the five stages below, from the Interconnection Request through post-commissioning model updates.

At a glance

Module: 093
Kind: Interconnection studies
Governing body: Southern Company
Applies to: Before and after commercial operation
Typical time: Follows the Southern Company interconnection calendar

Dashboard capabilities

  • Model Workspace Management: your plant's simulation model files kept in one dashboard workspace, with version tracking
  • PSCAD Simulations
  • PSS/E Simulations
  • Southern Company MQA Report Generation

Support services

What GridStrong does inside this module.

Stage 1: Cluster Request Window and Customer Engagement Window

  • Support you in preparing a valid Interconnection Request under LGIP Section 3.4.2 for the annual Cluster Request Window, including the Generating Facility technical data and models entered in SCT's online application tool (ICON for Cluster Study requests).
  • Develop site-specific plant models in the three formats SCT requires for IBRs: a PSS/E standard library (generic) model, a PSS/E user-defined model (UDM) and a PSCAD model, each as a standalone package at Continuous, Rated MW Output, per SCT's Model Submittal Requirements for Transmission Connected IBRs.
  • Build all three plant models with one aggregated unit and one aggregated unit transformer per identical IBR design, an equivalent collector system derived from your cable data, explicit main power transformers and shunt devices on the medium-voltage collector bus, and the station service load, flexible AC transmission system (FACTS) devices, plant controller and interconnection tie line that apply.
  • Coordinate with inverter, turbine and power plant controller manufacturers to obtain models, original equipment manufacturer (OEM) attestations that the IBR unit and plant controller models represent the planned equipment, and type test or hardware-in-the-loop (HIL) test results that validate the IBR unit model.
  • Check the PSS/E models against SCT's PSS/E requirements (PSS/E version 35, no library models the North American Electric Reliability Corporation (NERC) lists as unacceptable, bus numbers above 1000, table-driven UDMs, quarter-cycle minimum time step) and the PSCAD model against SCT's PSCAD requirements (actual control code where possible, transformer core saturation, negative sequence current injection, snapshot and multiple run support, no required time step below 10 microseconds and no required specific time step).
  • Perform the model performance attestation in Section 4 of SCT's Model Submittal Requirements (the MQA): run the required tests in a single-machine-infinite bus system on all three models (Initialization, Balanced Fault Ride-Through, Small Voltage Disturbance, Small Frequency Disturbance, High- and Low-Voltage Ride-Through, High- and Low-Frequency Ride-Through and Short Circuit Ratio tests) and on the PSCAD model alone (Unbalanced Fault and Phase Angle Change tests), plus the supplemental tests SCT recommends.
  • Benchmark the PSS/E standard library, PSS/E UDM and PSCAD responses by overlaying them on the same axes, tune the models toward alignment, and explain any remaining discrepancies as the attestation requires.
  • Prepare the Model Performance Attestation Report in SCT's Appendix A template and the completed Model Checklist; for a hybrid plant, report each resource type operating in parallel.
  • For a synchronous Generating Facility, prepare the generator, excitation system, governor and power system stabilizer model data that Attachment A to Appendix 1 of the LGIP requests.
  • Review the application package against the deficiencies SCT reports most often (technical data that does not match the single-line diagram, missing or inaccurate models, documentation, attestation report or checklist) before you submit, since no updates are accepted after the Cluster Request Window closes.
  • Prepare technical material for the Scoping Meeting in the Customer Engagement Window and update the models for any modification LGIP Section 4.4.1 permits before you execute the Cluster Study Agreement.

Stage 2: Cluster Study, Cluster Restudy and Interconnection Facilities Study

  • Review the Cluster Study Report (power flow, grounding review, reactive power, stability and short circuit analyses) and any Cluster Restudy Report for your request, and support you at the Cluster Study Report Meeting.
  • Assess plant-side mitigation, such as control tuning or reactive device changes, for issues the study assigns to your request, and prepare the updated models and attestation results that a modification request under LGIP Section 4.4 must carry.
  • Prepare the revised steady-state modeling data, single-line diagram inputs and dynamic modeling data for a technological advancement request under LGIP Section 4.4.6 when you change equipment before executing the Interconnection Facilities Study Agreement.
  • Respond to SCT data requests and model deficiency findings, and prepare the technical data due with the executed Interconnection Facilities Study Agreement.
  • Carry the weighted short circuit ratio (WSCR) and X/R (reactance to resistance) ratio at the Point of Interconnection (POI) from the interconnection study report into all later attestation tests, as SCT requires.

Stage 3: GIA Execution, Commencement of Work and Pre-Sync Activities

  • Prepare the non-confidential Generating Facility modeling data SCT requests after GIA execution, including the three-phase dynamic model and electric storage resource data, or confirm that the study models have not changed.
  • Develop the as-planned site-specific models (power flow, positive sequence, electromagnetic transient (EMT) and short circuit) reflecting the proposed equipment, control configuration and parameters, and protection settings, with verifying documentation.
  • Rerun the MQA on the as-planned models and update the Model Performance Attestation Report and Model Checklist.
  • Support you through SCT's Model Quality Check, Performance Evaluation and Detailed EMT Analysis: prepare responses to review comments, propose and model solutions to identified deficiencies for your decision, and prepare the updated models that reflect the chosen solution for you to submit.
  • Develop the as-built (pre-synchronization) models from the as-built equipment, control configuration and parameters, protection settings and plant controller settings, with supporting documentation such as nameplate photos, inverter settings snapshots and plant controller screenshots.

Stage 4: Trial Operation and Performance Validation Testing

  • Update the as-built models after commissioning when parameters change before Trial Operation Phase 2 (performance validation testing) begins.
  • Develop the final as-left models, including any changes made during performance validation testing, with documentation showing that the as-left equipment and parameters match the models.
  • Support your reactive power capability test on SCT's test template and the voltage step and capacitor bank test documentation.
  • Compare the as-left model response with the measured voltage and frequency step test response before submittal, and correct model-to-field mismatches.
  • For a synchronous Generating Facility, prepare the excitation system, speed governing system and power system stabilizer dynamic model data due before the Commercial Operation Date (COD), and support the power system stabilizer and frequency/speed step test documentation.
  • Support the root-cause investigation of deficiencies SCT finds during performance validation with simulations and model updates, toward SCT's approval of readiness for Commercial Operation.

Stage 5: Post-Commissioning

  • Update the models and the MQA report when you change equipment, inverter or plant controller firmware, control settings or protection settings, and prepare the documentation for SCT's evaluation of the change.
  • Update the dynamic, power flow and PSCAD models when you add energy storage or grid charging at an existing Generating Facility.
  • Support model verification and validation under NERC MOD-026-2, including EMT models benchmarked against positive sequence models, following the dynamic modeling requirements Southern Company Services issues as Planning Coordinator and Transmission Planner under MOD-026-2 Requirement R1.
  • Analyze measurement data SCT requests for event analysis, performance verification and model validation, and update the models where the measurements show the dynamics data should change.

Final deliverables

  • Stage 1: Site-specific PSS/E version 35 standard library and UDM packages (.raw or .sav, .dyr, .dll and documentation) and a PSCAD package (.pscx with supporting files and documentation); a Model Performance Attestation Report (MQA report) with overlaid PSS/E standard library, PSS/E UDM and PSCAD results; a completed Model Checklist.
  • Stage 2: A review memo of the Cluster Study and Cluster Restudy results for your request; updated model packages and MQA report for any modification or technological advancement request; responses to SCT data requests.
  • Stage 3: As-planned and as-built (pre-sync) model packages (power flow, PSS/E standard library and UDM, PSCAD and short circuit) with verification documentation, an updated MQA report and the completed Model Checklist; responses to SCT model review comments.
  • Stage 4: Post-commissioning as-built model update (if needed) and final as-left model packages with verification documentation; a model validation report comparing the as-left model response to the measured step test response; reactive power capability test support.
  • Stage 5: Updated model packages and MQA report for each change; model verification and validation documentation for MOD-026-2 submittals.

What we need from you

  • Project information: Point of Interconnection, Generating Facility Capacity (MW), requested Interconnection Service level and type (Energy Resource Interconnection Service or Network Resource Interconnection Service), and estimated In-Service, Initial Synchronization and Commercial Operation dates.
  • Single-line diagram of the Generating Facility, signed and stamped by a Professional Engineer licensed in the state where the facility is located, and the site layout map.
  • PSS/E (version 35) UDM files and dynamic link libraries, generic model parameters, and the PSCAD model of the IBR units and power plant controller from the OEMs, with user manuals, control narratives and control block diagrams.
  • OEM attestations for the IBR unit and power plant controller models, and type test or HIL test results for the IBR unit model.
  • Inverter or turbine datasheets, P-Q (real and reactive power) capability curves, harmonic spectrum and other equipment specification sheets the application requests.
  • Main power transformer and unit transformer test reports or nameplate data, including impedances, tap settings and core saturation characteristics.
  • Short-circuit contribution data of the Generating Facility: sub-transient and steady-state three-phase fault current at the POI and, where available, the inverter's positive and negative sequence current response to terminal voltage, as SCT's Pre-Sync Data Form for Solar & ESR Generation requests.
  • Balance of plant data: collector system cable schedule and parameters, interconnection tie line data, shunt reactive devices and their controls, FACTS devices, and station service load.
  • Plant controller settings, control modes and reference setpoints, and inverter voltage and frequency protection settings.
  • For electric storage resources: the state-of-charge range and the primary frequency response operating range.
  • For a synchronous Generating Facility: generator reactance and time constant data, and excitation system, governor and power system stabilizer models and constants.
  • The interconnection study report values of WSCR and X/R ratio at the POI.
  • During implementation: nameplate photos, inverter settings snapshots or configuration reports, and plant controller settings screenshots.
  • During Trial Operation: field measurement data from the voltage and frequency step tests and the reactive power capability test.

Assumptions and considerations

How the scope is bounded.

  • We provide the models compatible with PSS/E version 35 and with PSCAD version 5.0.0 or higher, Intel Fortran compiler version 15 or higher and Visual Studio 2015 or newer, per SCT's Model Submittal Requirements effective April 18, 2025. SCT reserves the right to require models for future PSS/E versions; a version conversion is a change in scope.
  • This module covers a new Interconnection Request entering an Annual Cluster Study under the current LGIP. The Order No. 2023 transitional study process is closed and does not apply. A Small Generating Facility (20 MW or less) requesting Energy Resource Interconnection Service follows the serial Study Process of the Small Generator Interconnection Procedures (Scoping Meeting, an optional Feasibility Study, System Impact Study and Facilities Study); one requesting Network Resource Interconnection Service enters the Annual Cluster Study under the LGIP. The same model submittal requirements apply, and our Stage 1 and Stage 2 services follow the study names of the process that applies.
  • Until the interconnection study report gives the WSCR and X/R ratio at the POI, the attestation tests use a short circuit ratio of 5 and an X/R ratio of 5, as SCT directs.
  • SCT's model requirements address fault ride-through capability, fault ride-through performance and converter-driven stability. Harmonic, power quality and other specialized analyses are not part of this module.
  • We prepare the applications, models and reports; you submit them to SCT through ICON, SIMPL or as SCT directs.
  • SCT runs its own Model Quality Check, Performance Evaluation and Detailed EMT Analysis. We respond to its findings but do not control its review time.
  • We rely on timely and accurate information from you, including OEM data and models; we assume no responsibility or liability for the accuracy of information supplied by you or your suppliers.
  • We do not guarantee the accuracy or quality of any models supplied by the OEMs.
  • This scope includes one round of corrections with the OEMs and engineering, procurement and construction (EPC) contractors per model submittal; further rounds are additional support, approved in writing.
  • We use engineering judgment and best practices where SCT's documents leave a modeling choice open.
  • Post-commissioning MOD-026-2 support follows the dynamic modeling requirements Southern Company Services issues as Planning Coordinator and Transmission Planner under MOD-026-2 Requirement R1. For an equipment or setting change after COD, SCT may require a full model package under the Model Submittal Requirements.

Run this module on one site.

Tell us the plant and the deadline. An engineer confirms the inputs, the schedule and what the Dashboard needs from you.