Modules · Interconnection studies · Module 098
PSLF, ASPEN OneLiner and PSCAD models, commissioning test support and study support through the Bonneville Power Administration's cluster process under Attachment L of its Open Access Transmission Tariff.
About this module
This package covers modeling and support for one or more interconnection requests to connect a Large Generating Facility (more than 20 MW, including electric storage) to the Bonneville Power Administration (BPA) transmission system. BPA studies new requests in clusters under Attachment L of its Open Access Transmission Tariff (OATT), the Standard Large Generator Interconnection Procedures (LGIP), effective October 1, 2025, and its Large Generator Interconnection Business Practice Version 13. A new request joins the Cluster Study that follows the Transition Cluster Study, which BPA begins after the Transition Cluster Study is complete, on at least 180 Calendar Days' notice (the Cluster Request Window for that Cluster Study opened January 27, 2025). The request proceeds through the Phase One Cluster Study, the Phase Two Cluster Study and the Interconnection Facilities Study, and after each cluster phase you must meet the commercial readiness, Site Control, model and technical data requirements of a Customer Review Period to continue. BPA tenders the Standard Large Generator Interconnection Agreement (LGIA) after it completes its National Environmental Policy Act (NEPA) review, and grants Commercial Operation only after the plant passes BPA's voltage and frequency control commissioning tests, you complete electromagnetic transient (EMT) ride-through studies with as-built models, and you answer BPA's modeling data requests. BPA's Technical Requirements for Interconnection to the BPA Transmission Grid (STD-N-000001) and its Interconnection Model Requirements (STD-N-000001-05) set the performance requirements and require models in GE PSLF or PowerWorld, ASPEN OneLiner and PSCAD formats. This package supports you through each of the five stages below, from the Interconnection Request through commissioning and post-commercial-operation model updates.
Module: 098
Kind: Interconnection studies
Governing body: BPA
Applies to: Before and after commercial operation
Typical time: Follows the BPA interconnection calendar
Support services
Assumptions and considerations
Other modules
Tell us the plant and the deadline. An engineer confirms the inputs, the schedule and what the Dashboard needs from you.