Modules · Interconnection studies · Module 100

APS Interconnection Module Package

Model packages, inverter-based resource business practice milestones and study support through Arizona Public Service's Cluster Study, from the Cluster Request Window to first-year model validation.

About this module

What this module covers.

This package covers modeling and support for one or more interconnection requests to the Arizona Public Service Company (APS) transmission system under the Large Generator Interconnection Procedures (LGIP) in Attachment O of the APS Open Access Transmission Tariff (OATT), as revised for Federal Energy Regulatory Commission (FERC) Order Nos. 2023 and 2023-A. APS accepts Interconnection Requests once a year in a Cluster Request Window that opens April 1, holds a Scoping Meeting during the Customer Engagement Window, and then runs a phased Cluster Study: Phase 1 (power flow and voltage analysis), Phase 2 (short circuit and stability analysis), Phase 3 (Cluster Re-Studies, if needed) and Phase 4 (Interconnection Facilities Study), followed by the Large Generator Interconnection Agreement (LGIA). Small Generating Facilities of 20 MW or less that are not eligible for, or do not pass, the Fast Track or 10 kW Inverter processes go through the Study Process of the Small Generator Interconnection Procedures (SGIP) in Attachment P, which uses the same Cluster Study; a Small Generating Facility that wants Network Resource Interconnection Service uses the LGIP. For inverter-based resources (IBR), the APS IBR Business Practice adds model, settings and performance testing milestones, set in the LGIA, that run through the first year after Commercial Operation. This package supports you through the Cluster Study, the Interconnection Facilities Study and LGIA, energization and commissioning, and post-commissioning model updates.

At a glance

Module: 100
Kind: Interconnection studies
Governing body: APS
Applies to: Before and after commercial operation
Typical time: Follows the APS interconnection calendar

Dashboard capabilities

  • Model Workspace Management: your plant's simulation model files kept in one dashboard workspace, with version tracking
  • PSCAD Simulations

Support services

What GridStrong does inside this module.

Stage 1: Cluster Request Window, Customer Engagement Window and Cluster Study Phase 1

  • Guide you through the Interconnection Request contents in LGIP Section 3.4.1.1 (Appendix 1 application, Site Control, Commercial Readiness Deposit, Point of Interconnection, Network Resource Interconnection Service (NRIS) or Energy Resource Interconnection Service (ERIS) election, and storage charging operating assumptions) and through APS deficiency notices; you submit the request through the APS PowerClerk portal.
  • Assemble the generator interconnection data package listed in Table 1 of the APS Application Requirements Business Practice: Inverter Based Resource Data Sheet, single-line diagram, site layout, manufacturer spec sheets with ambient temperature and elevation derating, and P-Q diagrams (four quadrants for storage).
  • Develop the site-specific power flow model (.epc) and dynamic model (.dyd) in GE PSLF format as a detailed equivalent from the generator terminals to the Point of Interconnection, following the equivalent modeling guidelines of the Western Electricity Coordinating Council (WECC) and the APS power flow checklist (control mode, Pmax, turbine and fuel type codes, station service load, transformer taps).
  • Build the generic library root-mean-square (RMS) dynamic model, with block diagrams of the inverter and plant controls, from Table 1 of LGIP Attachment A to Appendix 1 (or another WECC-approved model), and assemble the validated user-defined RMS model with its validation attestation. Use the WECC-approved plant controller model for plants with multiple generator equivalents (WECC has retired repc_b), enable voltage control and frequency response, and set the voltage and frequency ride-through models to the actual equipment settings.
  • Run the APS flat run and bump test (three-phase fault at the Point of Interconnection with APS standard clearing times) for all operating scenarios and document the results.
  • Perform the 0.95 power factor (reactive power) analysis with the APS method of two fictitious synchronous condensers and size any switched shunt capacitors planned in the collector system.
  • Develop or assemble the PSCAD electromagnetic transient (EMT) model and its documentation and review it against the APS Checklist for Reviewing Model Submission and PSCAD Model Supplier Checklist.
  • Coordinate with inverter, turbine and plant-level controller manufacturers to obtain PSLF and PSCAD models, parameters and model documentation.
  • Support the Scoping Meeting with technical data on the Point of Interconnection and alternatives, review the Phase 1 Report, and support your continue-or-withdraw election after the Phase 1 Report Meeting.

Stage 2: Cluster Study Phase 2 and Phase 3 (Cluster Re-Studies)

  • Review the Phase 2 Report (stability, short circuit, power factor and short circuit ratio results) and identify model-related causes of any instability or ride-through failure.
  • Provide modeling support over the course of Phase 2 and any Phase 3 Cluster Re-Study to resolve plant instability identified in the stability analysis, including control tuning, reactive device changes and updated models.
  • Screen the project against the APS EMT study screening criteria in Section 4.5 of the APS Technical Interconnection Requirements for IBRs (TIR) and support any EMT study APS performs.
  • Evaluate modifications permitted under LGIP Section 4.4 and prepare the revised Appendix 1 data and updated models that must accompany a modification request or an APS Material Modification evaluation under the APS Material Modifications Business Practice, including the analysis for a technological advancement request under LGIP Section 4.4.6.
  • Review re-study results to support your decisions at the Phase 2 and Phase 3 decision points, including the one-time NRIS to ERIS change APS allows before Phase 3 begins.
  • Prepare responses to APS data requests during the Cluster Study.

Stage 3: Interconnection Facilities Study (Cluster Study Phase 4), LGIA and Construction

  • Prepare the technical data required with the executed Interconnection Facilities Study Agreement.
  • Review the draft Interconnection Facilities Study Report and prepare technical comments for you to submit within the LGIP Section 8.3 comment period.
  • Support you on the technical content of the draft LGIA appendices, including Appendix C interconnection details and control technologies.
  • Prepare the LGIA Article 24.3 updated information submission: the completed Appendix 1 Generating Facility data with final equipment selections and models compatible with APS standard models.
  • Prepare the Power Plant Controller controls narrative support material and perform the Initial Model Testing milestone of the APS IBR Business Practice on the steady-state, positive-sequence dynamics and EMT models to show compliance with the TIR.
  • Run the TIR Table 4-1 tests in PSCAD and PSLF and benchmark the positive-sequence model against the EMT model per TIR Section 4.2.5.
  • Coordinate with equipment manufacturers on the equipment model quality attestations (E-MQA) and prepare the plant model quality attestation (P-MQA) material required by TIR Section 4.2.4.3.

Stage 4: Energization, Commissioning and As-Built Models

  • Update the PSLF and PSCAD models and the short circuit data to as-built design parameters for the LGIA Article 24.4 information supplementation before the Operation Date.
  • Prepare the As-Built Technical Documentation and Verified Models and As-Left Settings milestones of the APS IBR Business Practice, with as-left Power Plant Controller, inverter and relay settings implemented in the PSLF and PSCAD models.
  • Review inverter and relay protection and ride-through settings against the TIR and the North American Electric Reliability Corporation (NERC) ride-through standard that applies to the facility (PRC-029 for inverter-based resources, PRC-024 for synchronous and Type 1 and 2 wind units), including the PRC-024-2 and PRC-029-1 references in the APS testing documents.
  • Support you and your performance testing consultant on the commissioning tests in the APS Performance Testing and Compliance Guidelines for Solar PV or BESS (photovoltaic or battery energy storage system), including active and reactive power capability (MOD-025), voltage control modes (MOD-026), primary frequency response (MOD-027) and fast frequency response, with model simulations for comparison against field results.
  • Support the IBR Performance Requirements Test Report that you provide to APS.

Stage 5: Post-Commissioning Model Validation and Updates

  • Validate the PSLF and PSCAD models against field test data and prepare the validated models, model validation reports and NERC MOD-025, MOD-026 and MOD-027 reports due within one year after the Commercial Operation Date (COD) under the APS IBR Business Practice (the APS IBR Business Practice still cites MOD-027-1, which MOD-026-2 replaced on April 1, 2026).
  • Update models and settings documentation after equipment replacement, repair or adjustment for the LGIA Article 24.4 post-Operation Date information updates.
  • Evaluate proposed changes to IBR control settings or equipment against the APS FAC-002-4 R6 Qualified Change definition and the restudy triggers in TIR Section 4.6, and prepare the data and models you submit so APS can determine under LGIP Section 2.1 whether a Generating Facility Modification is a Material Modification.
  • Support the routine performance tests in Section 3.3 of the APS IBR Business Practice with updated model simulations.

Final deliverables

  • Stage 1: Interconnection Request technical data package for you to submit (GE PSLF .epc and .dyd models, flat run and bump test results, completed Inverter Based Resource Data Sheet, PSCAD EMT model with checklist review); a reactive power (0.95 power factor) analysis report; a Phase 1 Report review memo.
  • Stage 2: Phase 2 and Phase 3 report review memos with mitigation options; updated PSLF and PSCAD models for any LGIP Section 4.4 modification or APS data request.
  • Stage 3: Interconnection Facilities Study comment memo; LGIA Article 24.3 updated information package; Initial Model Testing results report with PSLF (.epc, .dyd) and PSCAD (.pscx or .pslx) models; PSLF versus PSCAD benchmarking report.
  • Stage 4: As-built PSLF and PSCAD models with as-left settings; as-built technical documentation package; protection and ride-through settings review memo; commissioning test simulation results.
  • Stage 5: Validated PSLF and PSCAD models with model validation reports; MOD-025, MOD-026 and MOD-027 reports; updated models and a qualified change evaluation memo for any post-COD modification.

What we need from you

  • Project information for the Appendix 1 Interconnection Request (or the SGIP Attachment 2 request for 20 MW or less): site location, Generating Facility Capacity and requested Interconnection Service level, summer and winter MW output, Point of Interconnection, NRIS or ERIS election, Commercial Operation Date, and storage charging operating assumptions with the control technologies that enforce them.
  • Inverter Based Resource Data Sheet (or Non-Inverter Based Generation Data Sheet), single-line diagram and site layout.
  • Manufacturer spec sheets, ambient temperature and elevation derating curves, and P-Q diagrams (four quadrants for storage).
  • Original equipment manufacturer (OEM) PSLF generic and user-defined dynamic models with parameters, OEM PSCAD models with documentation, firmware version and test cases, and manufacturer model quality attestations.
  • Generator step-up and medium voltage transformer nameplate and test report data (impedance, X/R, winding connections, taps and on-load tap changer data), collector system and gen-tie data with positive, negative and zero sequence values, and grounding transformer data.
  • Storage energy capacity (MWh), maximum charge and discharge rate, and state of charge limits.
  • Inverter and turbine voltage and frequency ride-through capabilities, protection and relay settings, the Power Plant Controller controls narrative and settings, and as-left settings at commissioning.
  • Harmonic source data and frequency-dependent impedances when APS requests power quality studies.
  • Field test data and commissioning test records for model validation.
  • Executed APS confidentiality agreement, critical energy infrastructure information (CEII) request form and extranet agreement for access to APS base case data.

Assumptions and considerations

How the scope is bounded.

  • APS performs its studies with GE PSLF power flow (.sav or .epc) and dynamic (.dyd) models, CAPE (.GDB) short circuit models and PSCAD (.pscx) EMT models. We deliver PSLF and PSCAD models compatible with the software versions APS names for the study; recent APS cluster study reports used PSLF versions 23.0.9 and 23.2.7.
  • PSCAD models meet the APS PSCAD Model Supplier Checklist, including compilation with PSCAD 4.5.3 or higher.
  • For facilities under the APS IBR Business Practice, APS lists a short circuit model in CAPE (.gdb) format among the required model submittals. We prepare the short circuit data that model needs: positive, negative and zero sequence impedances and the inverter fault contribution documentation in TIR Section 4.2.3. Building the CAPE .gdb file is outside this scope unless agreed.
  • We prepare the PSCAD EMT model with the Interconnection Request data package, as LGIP Attachment A to Appendix 1 requires. APS's 2026 Customer Information Presentation lists EMT models before the facilities study begins; the tariff controls.
  • This module follows the cluster process in the LGIP in Attachment O of the APS OATT as posted on the APS Open Access Same-Time Information System (OASIS) on July 13, 2026, which applies to requests submitted in an annual Cluster Request Window. The APS IBR Business Practice applies to IBR facilities of 10 MVA or more connected at 60 kV or higher with an initial LGIA signed after November 21, 2025. If APS revises these documents, we follow the version in effect for your request.
  • APS has asked FERC to revise LGIA Article 9.6.4.4, effective November 17, 2026 if accepted, so that electric storage resources that execute an LGIA after that date maintain APS advanced grid support specifications set in LGIA Appendix C. APS will post the model requirements and simulation tests in its IBR Business Practices. For storage and hybrid projects, we add those models and tests once APS posts them.
  • We prepare all requests, data packages and responses; you submit them to APS and execute all agreements.
  • Access to APS base case data requires you to request APS extranet access under the APS Base Case Data Business Practice (Confidentiality Agreement, CEII Request Form and Extranet Agreement). You list our engineers on Exhibit A of that Confidentiality Agreement as agents with a need to know, and we are bound in writing by confidentiality terms no less restrictive than APS's.
  • APS recommends listed consultants for IBR performance testing and model validation. For a consultant not on the list, you validate that it meets Section 2 of the APS Recommended Consultants document, including a Professional Engineer license, and notify APS. You select the testing consultant. Our Stage 4 scope is model-side support to that consultant. We perform the Stage 5 model validation and MOD-025, MOD-026 and MOD-027 reports after you validate us under Section 2 and notify APS; otherwise we support the consultant that performs them.
  • Interconnection service does not provide deliverability; transmission service requests are outside this scope.
  • We rely on you for timely and accurate information, including OEM models and equipment data; we assume no responsibility or liability for the accuracy of information supplied by you or your suppliers.
  • We do not guarantee the accuracy or quality of any models supplied by the OEMs.
  • This scope includes one round of corrections with the OEMs and engineering, procurement and construction (EPC) contractors per model or data request; further rounds are additional support, approved in writing.
  • We use engineering judgment and best practices where the governing documents do not specify a method.